CARGILL SHIPLOADER REPLACEMENT
Westwago, Louisiana
For this project, we replaced the existing ship loader within Tower 1 with a new Buhler ship loader at Cargill's Westwego, Louisiana, terminal facility. Our scope of work required removal of the existing ship loader and associated components, structural dafabet best bookmakerdemolitions, structural modifications to Tower 1 to accept the new unit, installation of a new transfer conveyor, and installation of the new ship loader with associated components. We performed commissioning as well as tests, trials, and system check-outs of the new shiploader, transfer conveyor, and modified dust system.